Building Progress, July 09, 2009

All photos by Brad Elliott
  • A front loader removes asphalt to create a new parking area near Physical Plant south of the campus road
  • A pump truck delivers concrete to workers below, creating the second floor of the east side of Winter Hall
  • Concrete is pumped into the rebar cages, creating the floor of the second level at Winter Hall
  • Workers reinforce the shoring on the west side of Winter Hall
  • The shoring outlines a two-story, 100-seat lecture hall at Winter Hall
  • Concrete trucks continually feed the giant pump truck that supplies concrete below to Winter Hall
  • A front loader moves dirt around Carr Field near a new retaining wall to the north
  • Crews pour concrete on the second level of eastern end Winter Hall
  • A water tender is used to keep the dust to a minimum during construction at Carr Field
  • The new observatory will house the Keck Telescope
  • A construction crew surveys the work at Winter Hall
  • Gravel is laid at the base of Adams Center before concrete is pumped on top of it
  • Workers are rebuilding Clark M, which was completely destroyed in the Tea Fire
  • As part of routine summer projects, each Clark Hall building is getting a new roof
More Photos