Building Updates

November 15, 2016

  • Construction of the Global Learning Center is now visible from outside the construction site.
  • Steel framing and pre-fabricated wood framing is going up on the north residence building. The wood framing for the second floor should begin to be visible in the next two weeks.
  • The steel framing has been delivered for the south residence building. A crane will begin placing steel very soon. The first floor wood wall framing is substantially complete for the residence rooms.
  • One more structural concrete pour is scheduled for the east side of the common building.
  • Installation of steel and wood framing will continue through Christmas break.
  • Plumbers and electricians are installing plumbing and electrical lines in the framed walls in both the north and south buildings.
  • Behind Van Kampen a mock-up is being constructed so the design and construction teams can see the details where materials like steel, stone and plaster intersect on the structure. The mock up also includes typical door and window installations.
  • Here are web cam photos from the site over the last month: http://webapps.westmont.edu/building/construction_cams.php